Happy Home Residency Cd

by Happy Home Residency
Certificate SignedP51700022362
Happy Home Residency CdProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700022362
Developer
Happy Home Residency
Project Bank
Bank of India
Proposed Possession
2021-09-30
Revised Possession
1900-01-01
Extended Possession
2022-03-30
Units Sold
0
Buildings
2
Project Area
861.27 sq.m
Total FSI
5999.85
MahaRERA QR
Happy Home Residency Cd
MahaRERA — P51700022362
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors14
✅Sanctioned14
🏗️Proposed Floors14
✅Sanctioned14

Apartment Configurations

HAPPY HOME RESIDENCY WIG D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK35.3947047
0%

HAPPY HOME RESIDENCY WING C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK50.8312012
0%
2BHK51.1912012
0%
2BHK57.7123023
0%
2BHK58.4324024
0%

Construction Progress

HAPPY HOME RESIDENCY WIG D

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor100%

HAPPY HOME RESIDENCY WING C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space100%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station90%
✅Energy managemcnt
✅Fire protection and fire safety requirements80%
✅Internal Roads & Footpaths50%
✅Landscaping & Tree Planting100%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains80%
✅Street Lighting75%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting100%