Hari ShrushtiProject photos will appear here when available.
Project Information
RERA Certificate No.
P51700020058
Registration No.
REA51700053966
Registration Date
2021-09-09
Developer
Shiv Shakti Developers Partnership
Architect
R K Khambayat
Project Bank
CANARA BANK
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
589.00 sq.m
Total FSI
940.80
Approved FSI
940.80
Hari Shrushti
MahaRERA — P51700020058
MahaRERA — P51700020058
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors5
✅Sanctioned5
Apartment Configurations
HARI SHRUSHTI
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 28.75 | 4 | 3 | 1 | 75% |
| 1 BHK | 30.03 | 4 | 2 | 2 | 50% |
| 1 BHK | 30.31 | 4 | 3 | 1 | 75% |
| 1 BHK | 30.6 | 4 | 2 | 2 | 50% |
| 1 BHK | 31.38 | 4 | 3 | 1 | 75% |
| 1 BHK | 31.42 | 1 | 1 | 0 | 100% |
| 1 BHK | 33.14 | 1 | 1 | 0 | 100% |
| SHOP | 13.02 | 1 | 1 | 0 | 100% |
| SHOP | 13.69 | 1 | 1 | 0 | 100% |
| SHOP | 15.3 | 3 | 2 | 1 | 67% |
Construction Progress
HARI SHRUSHTI
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting