Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
2023-12-30
Units Sold
0
Buildings
3
Project Area
3661.00 sq.m
Total FSI
3626.00
Approved FSI
3626.00
Haware Meadows Phase 1
MahaRERA — P52000015126
MahaRERA — P52000015126
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors8
✅Sanctioned8
Apartment Configurations
A Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 26.09 | 14 | 6 | 8 | 43% |
| 1BHK | 27.22 | 7 | 2 | 5 | 29% |
| 1BHK | 27.66 | 7 | 4 | 3 | 57% |
| 1RK | 19.38 | 14 | 10 | 4 | 71% |
| 2BHK | 36.33 | 7 | 4 | 3 | 57% |
| 2BHK | 36.71 | 7 | 5 | 2 | 71% |
| Shop | 13.23 | 2 | 1 | 1 | 50% |
| Shop | 16.12 | 1 | 0 | 1 | 0% |
| Shop | 17.46 | 6 | 0 | 6 | 0% |
| Shop | 19.68 | 1 | 0 | 1 | 0% |
| Shop | 76.81 | 1 | 0 | 1 | 0% |
B Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 27.22 | 7 | 1 | 6 | 14% |
| 1BHK | 26.09 | 14 | 5 | 9 | 36% |
| 1BHK | 27.66 | 7 | 0 | 7 | 0% |
| 1RK | 19.38 | 14 | 9 | 5 | 64% |
| 2 BHK | 36.33 | 7 | 3 | 4 | 43% |
| 2BHK | 36.71 | 7 | 2 | 5 | 29% |
| Shop | 13.23 | 2 | 1 | 1 | 50% |
| Shop | 16.12 | 2 | 1 | 1 | 50% |
| Shop | 17.46 | 6 | 1 | 5 | 17% |
C Wing
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 27.85 | 14 | 11 | 3 | 79% |
| 1BHK | 28.01 | 14 | 8 | 6 | 57% |
| 1BHK | 33.96 | 14 | 0 | 14 | 0% |
Construction Progress
A Wing
B Wing
C Wing
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting100%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%