HIRANI REGENCY

by HIRANI LIFESPACES Partnership
Certificate SignedP99000007111
HIRANI REGENCYProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000007111
Registration No.
REA99000014695
Registration Date
2017-08-17
Developer
HIRANI LIFESPACES Partnership
Architect
Nishant Prabhakar Patil
Project Bank
INDIAN OVERSEAS BANK
Proposed Possession
2024-11-30
Units Sold
0
Buildings
3
Project Area
3000.00 sq.m
Total FSI
2216.91
Approved FSI
2216.91
MahaRERA QR
HIRANI REGENCY
MahaRERA — P99000007111
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6

Apartment Configurations

Hirani Regency Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.19220
100%
1 BHK35.4431
75%
1 BHK39.22826
25%
2 BHK48.4422
50%

Hirani Regency Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.24220
100%
1 BHK37.31550
100%
1 BHK38.1615
17%
1 BHK38.2523
40%

Hirani Regency Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.19312
33%
1 BHK36.14413
25%
1 BHK39.22440
100%
1 BHK40.15413
25%
2 BHK44.08211
50%
2 BHK48.4220
100%

Construction Progress

HIRANI REGENCY WING A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

HIRANI REGENCY WING B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

HIRANI REGENCY WING C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths50%
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains70%
✅Street Lighting100%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%