INDRAPRASTH COMPLEX
by SWASTIK DEVELOPERS
Partnership
Project Information
RERA Certificate No.
P99000001847
Registration No.
REA99000006589
Registration Date
2017-07-29
Developer
SWASTIK DEVELOPERS Partnership
Architect
Mahendra Kale
Project Bank
VASAI VIKAS SAHAKARI BANK LIMITED
Proposed Possession
2019-01-31
Revised Possession
2019-01-31
Extended Possession
2022-04-30
Units Sold
0
Buildings
3
Project Area
2990.00 sq.m
Total FSI
3126.50
Approved FSI
2365.00
INDRAPRASTH COMPLEX
MahaRERA โ P99000001847
MahaRERA โ P99000001847
Scan to verify on MahaRERA portal
Wing-wise Details
๐๏ธProposed Floors6
โ
Sanctioned6
๐
ฟ๏ธClosed Parking1
๐
Completion2020-01-31
๐๏ธProposed Floors6
โ
Sanctioned6
๐
ฟ๏ธClosed Parking1
๐
Completion2020-01-31
๐๏ธProposed Floors6
โ
Sanctioned6
๐
ฟ๏ธClosed Parking1
๐
Completion2020-01-31
Apartment Configurations
Building No 1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 33.88 | 4 | 4 | 0 | 100% |
| 1 BHK | 34.76 | 8 | 8 | 0 | 100% |
| 1 BHK | 35.89 | 8 | 8 | 0 | 100% |
| 2 BHK | 46.65 | 4 | 4 | 0 | 100% |
Building No 2
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 33.88 | 4 | 4 | 0 | 100% |
| 1 BHK | 34.76 | 8 | 8 | 0 | 100% |
| 1 BHK | 35.89 | 8 | 8 | 0 | 100% |
| 2 BHK | 46.65 | 4 | 4 | 0 | 100% |
Building No 3
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 33.88 | 4 | 4 | 0 | 100% |
| 1 BHK | 34.76 | 8 | 6 | 2 | 75% |
| 1 BHK | 35.89 | 4 | 4 | 0 | 100% |
| 2 BHK | 46.65 | 4 | 3 | 1 | 75% |
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 33.880001068115234 | 0 | 0 | 0 | 0% |
| 1Bhk | 34.7599983215332 | 0 | 0 | 0 | 0% |
| 1Bhk | 35.88999938964844 | 0 | 0 | 0 | 0% |
| 2Bhk | 46.650001525878906 | 0 | 0 | 0 | 0% |
Construction Progress
BUILDING NO 1
BUILDING NO 2
BUILDING NO 3
RERA Registered Amenities
โฌAggregate area of recreational Open Space
โฌCommunity Buildings
โ
Electrical Meter Room, Sub-Station, Receiving Station100%
โ
Energy management100%
โฌFire Protection And Fire Safety
Requirements
โ
Landscaping & Tree Planting100%
โฌOpen Parking
โ
Sewerage (Chamber, Lines, Septic Tank , STP)100%
โฌSolid Waste Management And Disposal
โ
Storm Water Drains100%
โฌStreet Lighting
โฌTreatment And Disposal Of Sewage And Sullage Water
โ
Water Conservation, Rain water Harvesting100%
โ
Water Supply75%