📞 +91 98200 30685 ✉️
RERA: A51800043517

Ivy Dreamland Phase 1

by Leal Developers Partnership
Certificate Signed P99000051683
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P99000051683
Registration No.
REA99000138018
Registration Date
2024-04-24
Developer
Leal Developers Partnership
Architect
En Con
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2026-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
13
Units Sold
3 (23%)
Buildings
15
Project Area
7238.66 sq.m
Total FSI
1695.09
Approved FSI
1695.09
MahaRERA QR
Ivy Dreamland Phase 1
MahaRERA — P99000051683
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
📅Completion2026-06-30
📅Completion2026-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors3
Sanctioned3
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🅿️Closed Parking1
📅Completion2026-06-30

Apartment Configurations

Type 1

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 100.25 1 0 1
0%

Type 10

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 138.86 1 0 1
0%

Type 11

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 136.48 1 0 1
0%

Type 12

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 219.27 0 0 0
0%

Type 13

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 209.95 0 0 0
0%

Type 14 Rh 2

Type Carpet (sq.ft) Total Booked Available Status
ROW HOUSE 95.02 1 0 1
0%

Type 14 Rh1

Type Carpet (sq.ft) Total Booked Available Status
ROW HOUSE 96.42 1 0 1
0%

Type 2

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 91.38 1 0 1
0%

Type 3

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 88.2 1 0 1
0%

Type 4

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 99.44 1 0 1
0%

Type 5

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 90.55 1 0 1
0%

Type 6

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 90.74 1 0 1
0%

Type 7

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 91.34 1 0 1
0%

Type 8

Type Carpet (sq.ft) Total Booked Available Status
Bungalow 91.54 1 0 1
0%

Construction Progress

TYPE 1

Basement (if any)100%

Type 1

Excavation100%

TYPE 1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 1

Plinth100%
Podiums (if any) 0%

Type 1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 1

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 1

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 10

Basement (if any)100%

Type 10

Excavation100%

TYPE 10

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%

Type 10

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

TYPE 10

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Type 10

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%
Overall Percentage of Completion of the work done For the entire Building /Wing65%

TYPE 10

Plinth100%
Podiums (if any) 0%

Type 10

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

TYPE 10

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Type 10

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

TYPE 10

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Type 10

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 11

Basement (if any)100%

Type 11

Excavation100%

TYPE 11

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%

Type 11

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

TYPE 11

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Type 11

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%
Overall Percentage of Completion of the work done For the entire Building /Wing65%

TYPE 11

Plinth100%
Podiums (if any) 0%

Type 11

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

TYPE 11

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Type 11

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

TYPE 11

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Type 11

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 12

Basement (if any)100%

Type 12

Excavation100%

TYPE 12

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Type 12

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

TYPE 12

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Type 12

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

TYPE 12

Plinth100%
Podiums (if any) 0%

Type 12

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

TYPE 12

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Type 12

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

TYPE 12

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Type 12

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

TYPE 13

Basement (if any)100%

Type 13

Excavation100%

TYPE 13

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Type 13

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

TYPE 13

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Type 13

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

TYPE 13

Plinth100%
Podiums (if any) 0%

Type 13

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

TYPE 13

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Type 13

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

TYPE 13

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Type 13

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

TYPE 14 RH 2

Basement (if any)100%

Type 14 Rh 2

Excavation100%

TYPE 14 RH 2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Type 14 Rh 2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

TYPE 14 RH 2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Type 14 Rh 2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

TYPE 14 RH 2

Plinth100%
Podiums (if any) 0%

Type 14 Rh 2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

TYPE 14 RH 2

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Type 14 Rh 2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

TYPE 14 RH 2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Type 14 Rh 2

Stilt Floor50%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

TYPE 14 RH1

Basement (if any)100%

Type 14 Rh1

Excavation100%

TYPE 14 RH1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Type 14 Rh1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

TYPE 14 RH1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Type 14 Rh1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

TYPE 14 RH1

Plinth100%
Podiums (if any) 0%

Type 14 Rh1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

TYPE 14 RH1

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Type 14 Rh1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

TYPE 14 RH1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Type 14 Rh1

Stilt Floor50%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

TYPE 2

Basement (if any)100%

Type 2

Excavation100%

TYPE 2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 2

Plinth100%
Podiums (if any) 0%

Type 2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 2

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 2

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 3

Basement (if any)100%

Type 3

Excavation100%

TYPE 3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 3

Plinth100%
Podiums (if any) 0%

Type 3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 3

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 3

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 4

Basement (if any)100%

Type 4

Excavation100%

TYPE 4

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 4

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 4

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 4

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 4

Plinth100%
Podiums (if any) 0%

Type 4

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 4

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 4

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 4

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 4

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 5

Basement (if any)100%

Type 5

Excavation100%

TYPE 5

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 5

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 5

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 5

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 5

Plinth100%
Podiums (if any) 0%

Type 5

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 5

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 5

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 5

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 5

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 6

Basement (if any)100%

Type 6

Excavation100%

TYPE 6

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 6

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 6

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 6

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 6

Plinth100%
Podiums (if any) 0%

Type 6

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 6

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 6

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 6

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 6

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 7

Basement (if any)100%

Type 7

Excavation100%

TYPE 7

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 7

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 7

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 7

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 7

Plinth100%
Podiums (if any) 0%

Type 7

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 7

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 7

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 7

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 7

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 8

Basement (if any)100%

Type 8

Excavation100%

TYPE 8

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 8

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 8

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 8

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 8

Plinth100%
Podiums (if any) 0%

Type 8

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 8

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 8

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 8

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 8

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

TYPE 9

Basement (if any)100%

Type 9

Excavation100%

TYPE 9

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Type 9

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%

TYPE 9

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Type 9

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%

TYPE 9

Plinth100%
Podiums (if any) 0%

Type 9

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%

TYPE 9

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Type 9

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%

TYPE 9

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Type 9

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 40%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 40%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 40%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 40%
Solid Waste Management And Disposal 40%
Storm Water Drains 40%
Street Lighting 40%
Treatment And Disposal Of Sewage And Sullage Water 40%
Water Conservation, Rain water Harvesting 40%
Water Supply 40%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.