Jayagarden Phase 2

by Bhoir Builders And Developers
Certificate SignedP51700019823
Jayagarden Phase 2Project photos will appear here when available.

Project Information

RERA Certificate No.
P51700019823
Developer
Bhoir Builders And Developers
Project Bank
City Union Bank Ltd
Proposed Possession
2022-12-25
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
8980.00 sq.m
Total FSI
10940.89
Approved FSI
7052.00
MahaRERA QR
Jayagarden Phase 2
MahaRERA — P51700019823
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🏗️Proposed Floors6
Sanctioned6
🏗️Proposed Floors9
Sanctioned9

Apartment Configurations

Bldg No 01

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK48.6728028
0%
Shop11.96404
0%
Shop12.6101
0%

Bldg No 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK32.41101
0%
2BHK48.6716016
0%

Bldg No 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK18.1101
0%
2BHK48.6727027
0%

Construction Progress

Bldg No 01

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
Stilt Floor80%

Bldg No 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
Stilt Floor80%

Bldg No 6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
Stilt Floor80%

RERA Registered Amenities

Aggregate area of recreational Open Space20%
Community Buildings
Electrical meter room, sub-station, receiving station50%
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths60%
Landscaping & Tree Planting70%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Solid Waste Management And Disposal
Storm Water Drains50%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water
Water Supply50%
Water conservation /Rain water harvesting