Project Information
RERA Certificate No.
P99000029993
Registration No.
REA99000091552
Developer
Kishor Patil
Architect
Shri Ashok Krishna Rengade
Project Bank
DOMBIVLI NAGARI SAHAKARI BANK LTD
Proposed Possession
2023-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Buildings
3
Project Area
2369.45 sq.m
Total FSI
2369.45
Jivdani Vaibhavlaxmi
MahaRERA — P99000029993
MahaRERA — P99000029993
Scan to verify on MahaRERA portal
Wing-wise Details
🚗Open
Parking15
🅿️Closed Parking6
📅Completion2023-12-31
🚗Open
Parking15
📅Completion2023-12-31
🚗Open
Parking15
🅿️Closed Parking6
📅Completion2023-12-31
Apartment Configurations
Jivdani Vaibhavlaxmi Building No 1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 28.34 | 1 | 0 | 1 | 0% |
| 1 BHK | 31.13 | 4 | 0 | 4 | 0% |
| 1 BHK | 36.43 | 4 | 0 | 4 | 0% |
| 1RK | 18.4 | 1 | 0 | 1 | 0% |
| 1RK | 19.79 | 1 | 0 | 1 | 0% |
| 1RK | 23.32 | 4 | 0 | 4 | 0% |
| 1RK | 24.25 | 8 | 0 | 8 | 0% |
Jivdani Vaibhavlaxmi Building No 2
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 32.8 | 5 | 0 | 5 | 0% |
| 1 BHK | 33.92 | 5 | 0 | 5 | 0% |
| 1RK | 21.56 | 4 | 0 | 4 | 0% |
Jivdani Vaibhavlaxmi Building No 3
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 31.31 | 1 | 0 | 1 | 0% |
| 1 BHK | 33.27 | 4 | 0 | 4 | 0% |
| 1 BHK | 34.38 | 5 | 0 | 5 | 0% |
| 1RK | 20.91 | 1 | 0 | 1 | 0% |
| 1RK | 22.3 | 4 | 0 | 4 | 0% |
| 1RK | 22.76 | 5 | 0 | 5 | 0% |
| 1RK | 24.34 | 4 | 0 | 4 | 0% |
| 1RK | 25.74 | 4 | 0 | 4 | 0% |
Construction Progress
Jivdani Vaibhavlaxmi Building No 1
Jivdani Vaibhavlaxmi Building No 2
Jivdani Vaibhavlaxmi Building No 3
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station70%
✅Energy management60%
✅Fire Protection And Fire Safety
Requirements60%
✅Landscaping & Tree Planting70%
✅Open Parking70%
✅Sewerage (Chamber, Lines, Septic Tank , STP)85%
✅Solid Waste Management And Disposal85%
⬜Storm Water Drains
✅Street Lighting90%
⬜Treatment And Disposal Of Sewage And Sullage Water
⬜Water Conservation, Rain water Harvesting
✅Water Supply75%