K K PARK - PHASE I
by K.K.CONSTRUCTION
Partnership
Project Information
RERA Certificate No.
P99000024440
Registration No.
REA99000068750
Registration Date
2021-09-08
Developer
K.K.CONSTRUCTION Partnership
Architect
Shrikant Yevale
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2025-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
13200.00 sq.m
Total FSI
14256.00
Approved FSI
11370.64
K K PARK - PHASE I
MahaRERA — P99000024440
MahaRERA — P99000024440
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors9
✅Sanctioned9
🅿️Closed Parking1
📅Completion2025-12-30
🏗️Proposed Floors9
✅Sanctioned9
🅿️Closed Parking1
📅Completion2025-06-30
🏗️Proposed Floors9
✅Sanctioned9
🅿️Closed Parking18
📅Completion2024-11-30
🏗️Proposed Floors9
✅Sanctioned9
🅿️Closed Parking18
📅Completion2023-12-31
Apartment Configurations
A-1 Type
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 37.16 | 28 | 0 | 28 | 0% |
| 2 BHK | 47.14 | 28 | 0 | 28 | 0% |
A-2 Type
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 37.16 | 28 | 5 | 23 | 18% |
| 2 BHK | 47.14 | 28 | 0 | 28 | 0% |
A-3Type
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 37.16 | 28 | 0 | 28 | 0% |
| 2 BHK | 47.14 | 28 | 3 | 25 | 11% |
A-4 Type
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 37.16 | 28 | 14 | 14 | 50% |
| 2 BHK | 47.14 | 28 | 17 | 11 | 61% |
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk | 37.15999984741211 | 0 | 0 | 0 | 0% |
| 2Bhk | 47.13999938964844 | 0 | 0 | 0 | 0% |
Construction Progress
A-1 TYPE
A-2 TYPE
A-3TYPE
A-4 TYPE
RERA Registered Amenities
✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station10%
⬜Energy management
✅Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting60%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)20%
✅Solid Waste Management And Disposal
⬜Storm Water Drains
✅Street Lighting25%
✅Treatment And Disposal Of Sewage And Sullage Water40%
⬜Water Conservation, Rain water Harvesting
✅Water Supply100%