📞 +91 98200 30685✉️
RERA: A51800043517

K M Avenue

by K M Enterprises
Kept in AbeyanceP99000006092

Project Information

RERA Certificate No.
P99000006092
Registration No.
REA99000011689
Developer
K M Enterprises
Project Bank
KOTAK MAHINDRA BANK
Proposed Possession
2014-11-30
Revised Possession
2018-10-31
Extended Possession
2022-12-31
Buildings
1
Project Area
4555.06 sq.m
Total FSI
3416.29
MahaRERA QR
K M Avenue
MahaRERA — P99000006092
Scan to verify on MahaRERA portal

Wing-wise Details

📅Completion1900-01-01

Apartment Configurations

Building No 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FLAT27.0440
100%
FLAT28.0454513
94%
FLAT29.95101
0%
FLAT30.1110
100%
FLAT30.5330
100%
FLAT31.98431
75%
FLAT35.3880
100%
FLAT39.9440
100%
FLAT41.3330
100%
FLAT42.77110
100%
SHOP4.32220
100%
SHOP5.78220
100%
SHOP6.1110
100%
SHOP7.36422
50%
SHOP7.76110
100%
SHOP8.03110
100%
SHOP9.07110
100%
SHOP9.18110
100%
SHOP9.59110
100%
SHOP12.42413
25%
SHOP12.57110
100%

Construction Progress

Building No 9

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate90%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing89%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now