Project Information
RERA Certificate No.
P99000020091
Developer
Krisha Associates
Architect
Architect Roshan Patil &Amp; Associates
Project Bank
HDFC BANK
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Buildings
2
Project Area
2107.48 sq.m
Total FSI
2022.83
Kavya Apartment
MahaRERA — P99000020091
MahaRERA — P99000020091
Scan to verify on MahaRERA portal
Wing-wise Details
📅Completion2022-12-31
📅Completion2022-12-31
Apartment Configurations
Type B2
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 30.82 | 10 | 1 | 9 | 10% |
| 1 BHK | 30.99 | 5 | 3 | 2 | 60% |
| 1RK | 22.83 | 10 | 3 | 7 | 30% |
| 2 BHK | 42.32 | 5 | 0 | 5 | 0% |
Type B3
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 30.82 | 9 | 4 | 5 | 44% |
| 1 BHK | 30.99 | 5 | 2 | 3 | 40% |
| 1RK | 22.06 | 1 | 0 | 1 | 0% |
| 1RK | 22.83 | 10 | 0 | 10 | 0% |
| 2 BHK | 42.32 | 5 | 1 | 4 | 20% |
Construction Progress
Type B2
Type B3
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station
⬜Energy management
⬜Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting
✅Water Supply