KELVA

by UVA HOMES LLP
Certificate SignedP99000017341
KELVAProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000017341
Developer
UVA HOMES LLP
Architect
RENDER POINT
Project Bank
BASSIEN CATHOLIC CO OPERATIVE BANK LTD
Proposed Possession
2027-04-30
Revised Possession
1900-01-01
Extended Possession
2025-12-31
Total Units
27
Units Sold
9 (33%)
Buildings
1
Project Area
598.30 sq.m
Total FSI
598.30
MahaRERA QR
KELVA
MahaRERA — P99000017341
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏠Habitable5
🔢Total Units27
🏡Residential20
🏢Non-Residential7

Apartment Configurations

KELVA PARADISE

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK30.25404
0%
FLAT30.52835
38%
FLAT30.79844
50%
SHOP3.96110
100%
SHOP6.69101
0%
SHOP8.78101
0%
SHOP8.97101
0%
SHOP8.99211
50%
SHOP9.17101
0%

Construction Progress

KELVA PARADISE

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor80%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths25%
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply10%
✅Water conservation /Rain water harvesting