Proposed Possession
2028-03-31
Total Units
32
Units Sold
0 (0%)
Project Area
443.00 sq.m
Total FSI
1329.25
Approved FSI
1329.25
MahaRERA QR
Krisha Heights
MahaRERA — P99000056276
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🏠Habitable7
🔢Total Units32
🏡Residential32
🚗Open Parking15
🅿️Closed Parking3
📅Completion2028-03-31

Apartment Configurations

Krisha Heights

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK26.71606
0%
1 BHK31.28606
0%
1 BHK32.97707
0%
1 BHK35.43606
0%
1 BHK36.07707
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk26.709999084472656000
0%
1Bhk31.280000686645508000
0%
1Bhk32.970001220703125000
0%
1Bhk35.43000030517578000
0%
1Bhk36.06999969482422000
0%

Construction Progress

Krisha Heights

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure57%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now