43
Units
2026
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Oct 2026
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Shop85–134 ftΒ²On request
1 BHK280–305 ftΒ²On request
2 BHK686 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P51700054317
Registered
2024-01-15
Litigation
None on record
Escrow Bank
ICICI BANK LIMITED
Architect
A S Dastane & Associates
Total FSI
1519
04

Buildings Β· 1 Wing(s)

Building 18 floors Β· 43 units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Ambernath
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

NILESH DNYANESHWAR KONKARPartner
RAM SHANKAR GAIKWADPartner
RAVI KANTA GAIKWADPartner
09

Construction Progress

50% avg
Basement (if any)100%
Excavation100%
Plinth100%
Podiums (if any) 100%
Slabs of Super Structure100%
Stilt Floor100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
08

Property Rates in Ambernath

Residential Β· Sale
β‚Ή6,000–10,000/sqft
Commercial Β· Sale
β‚Ή6,500–9,500/sqft
2 BHK Β· Rent
β‚Ή10,000–30,000/mo
14

More by Tulsi Kimaya Construction

Tulsi AlayaUlwe Β· Sold OutTulsi SonataNew Panvel Β· Sold Out
15

MahaRERA projects nearby in Ambernath

Patels Pristine432 unitsWALEKAR HOMES323 unitsOM SAI PALMS246 unitsAdiyogi Blossom235 unitsMohan Precious Greens Phase Iii228 unitsShubh Vastu Wing B And C227 unitsV A Business Centre184 unitsIskcon Residency Phase 1182 unitsPrecious Harmony Nx179 unitsGnp Galaxy Phase - Iii173 unitsAmrut Manjil173 unitsKrishna Nayan Complex Phase I171 units
?

Frequently Asked Questions

When is possession of Krishna Glory?

As per MahaRERA, proposed possession is Oct 2026.

Is Krishna Glory RERA-registered?

Yes β€” MahaRERA registration P51700054317, registered 2024-01-15. No litigations on record.

Who is the developer?

Tulsi Kimaya Construction β€” 3 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Ambernath β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P52000016540β˜… Featured
The Wadhwa Group
Wadhwa Wise City, New Panvel
1 BHK, 2 BHK, 3 BHK Β· β‚Ή16,946/sq.ft Β· Possession 2026-12-01 00:00:00
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’