List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Kuber Heights

by United Construction Co. Partnership
Certificate SignedP51800023657
Kuber HeightsProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800023657
Registration No.
REA51800066403
Registration Date
2021-09-08
Developer
United Construction Co. Partnership
Architect
Design Crest
Project Bank
IDBI BANK
Proposed Possession
2028-04-30
Revised Possession
1900-01-01
Extended Possession
2025-12-30
Total Units
136
Units Sold
113 (83%)
Buildings
2
Project Area
1805.70 sq.m
Total FSI
10714.15
Approved FSI
8789.15
MahaRERA QR
Kuber Heights
MahaRERA — P51800023657
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
✅Sanctioned20
🏠Habitable20
🔢Total Units21
🏡Residential21
🏗️Proposed Floors15
✅Sanctioned15
🏠Habitable15
🔢Total Units115
🏡Residential115

Apartment Configurations

ASHTAVINAYAKCHS LTD WING B REHAB BUILDING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK27.8721318
14%

WING A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK40.5123716
30%
1BHK40.97461729
37%
2BHK63.08461234
26%

Construction Progress

ASHTAVINAYAKCHS LTD WING B REHAB BUILDING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

WING A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises40%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks68%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now