List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Kulswamini

by Shree Sai Builders Partnership
Certificate SignedP51700048200
KulswaminiProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700048200
Registration No.
REA51700123036
Registration Date
2022-12-15
Developer
Shree Sai Builders Partnership
Architect
Swastik Creation
Project Bank
TJSB SAHAKARI BANK LTD
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
58
Units Sold
33 (57%)
Buildings
2
Project Area
1032.58 sq.m
Total FSI
2520.75
Approved FSI
2520.75
MahaRERA QR
Kulswamini
MahaRERA — P51700048200
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors7
✅Sanctioned7
🏠Habitable7
🔢Total Units31
🏡Residential21
🏢Non-Residential10
🏗️Proposed Floors8
✅Sanctioned8
🏠Habitable7
🔢Total Units27
🏡Residential27

Apartment Configurations

KULSWAMINI A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK35.11743
57%
1BHK41.33101
0%
2BHK44.4734
43%
2BHK50.63606
0%
Shop10.16101
0%
Shop10.19211
50%
Shop11.07101
0%
Shop11.61101
0%
Shop13.07101
0%
Shop16.85101
0%
Shop24.41110
100%
Shop26.65101
0%

KULSWAMINI B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK33.26725
29%
1BHK34.34624
33%
1BHK34.98743
57%
1BHK36.19642
67%
2BHK45.18101
0%

Construction Progress

KULSWAMINI A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

KULSWAMINI B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%

Latest Mumbai Property News