List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Lotus Park

by Real Enterprise Partnership
Certificate SignedP51700020522
Lotus ParkProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700020522
Registration No.
REA51700055193
Registration Date
2021-09-09
Developer
Real Enterprise Partnership
Architect
Mahendra Sharma
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
1025.00 sq.m
Total FSI
1229.95
Approved FSI
1229.95
MahaRERA QR
Lotus Park
MahaRERA — P51700020522
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🏗️Proposed Floors6
Sanctioned6

Apartment Configurations

BUILDING NO 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK TYPE137.54431
75%
1BHK TYPE236.26624
33%
1BHK TYPE336.52220
100%
1BHK TYPE437.33431
75%

BUILDING NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK TYPE152.34220
100%
2BHK TYPE251.63211
50%
2BHK TYPE354.67211
50%
2BHK TYPE454.21202
0%

Construction Progress

BUILDING NO 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises45%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor100%

BUILDING NO 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.87%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises91%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises81%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now