List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

MADHAV VATIKA VIII

by R M N H DEVELOPERS LLP Partnership
Certificate SignedP99000050367
MADHAV VATIKA VIIIProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000050367
Registration No.
REA99000133211
Registration Date
2023-04-05
Developer
R M N H DEVELOPERS LLP Partnership
Architect
CREATIVE ASSOCIATES
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2027-10-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
43
Units Sold
11 (26%)
Buildings
2
Project Area
1210.16 sq.m
Total FSI
2129.81
Approved FSI
2129.81
MahaRERA QR
MADHAV VATIKA VIII
MahaRERA — P99000050367
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors1
Sanctioned1
🏠Habitable1
🔢Total Units1
🏡Residential1
🏗️Proposed Floors6
Sanctioned6
🏠Habitable6
🔢Total Units42
🏡Residential42

Apartment Configurations

BUILDING NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK113.74101
0%

BUILDING NO-1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK30.3710010
0%
1RK20.91101
0%
1RK22.65101
0%
2BHK37.5220020
0%
2BHK39.01514
20%
2BHK42.49505
0%

Construction Progress

BUILDING NO 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO-1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply100%
Water conservation /Rain water harvesting