Magic Hill Enclave

by Garnet Construction Ltd. Company
Certificate SignedP52000004503
Magic Hill EnclaveProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000004503
Registration No.
REA52000009449
Registration Date
2021-09-09
Developer
Garnet Construction Ltd. Company
Architect
Adinath Patkar
Project Bank
STATE BANK OF INDIA
Proposed Possession
2028-04-30
Revised Possession
2022-12-30
Extended Possession
2023-12-29
Total Units
132
Units Sold
113 (86%)
Buildings
131
Project Area
64274.00 sq.m
Total FSI
18557.73
Approved FSI
18557.73
MahaRERA QR
Magic Hill Enclave
MahaRERA — P52000004503
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors3
✅Sanctioned3
🏠Habitable3
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1

Apartment Configurations

Bungalow 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 10

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 100

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 101

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 102

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 103

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 104

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 105

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 106

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 107

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 108

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 109

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 11

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 110

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 111

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 112

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 113

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 114

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 115

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 116

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 117

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 118

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 119

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 12

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 120

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 121

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 122

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 123

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 124

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 125

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 126

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 127

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 128

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 129

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 13

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 130

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 131

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 14

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 15

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 16

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 17

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 18

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 19

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow83.86110
100%

Bungalow 20

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 21

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 22

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 23

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 24

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 25

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 26

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 27

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 28

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 29

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow83.86110
100%

Bungalow 30

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 31

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 32

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 33

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 34

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 35

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 36

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 38

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 39

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow83.86110
100%

Bungalow 40

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 41

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 42

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 43

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 44

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 45

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 46

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 47

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 48

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 49

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow83.86110
100%

Bungalow 50

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 51

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 52

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 53

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 54

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 55

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 56

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 57

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 58

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 59

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 60

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 61

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 62

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 63

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow108.99110
100%

Bungalow 64

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 65

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 66

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 67

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 68

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 69

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 70

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 71

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 72

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 73

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 74

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 75

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 76

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 77

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 78

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 79

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 80

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 81

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 82

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 83

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 84

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 85

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 86

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 87

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 88

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 89

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 90

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 91

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 92

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 93

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 94

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 95

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 96

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Bungalow 97

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 98

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow125.23110
100%

Bungalow 99

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow128.06110
100%

Plot 37

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Plot—000
0%

Construction Progress

Bangalow 37

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 10

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 100

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 101

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 102

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 103

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises22%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 104

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 105

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 106

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 107

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 108

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 109

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 11

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 110

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 111

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 112

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 113

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 114

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 115

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 116

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 117

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 118

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 119

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 12

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 120

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 121

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 122

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 123

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 124

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 125

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 126

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 127

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 128

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 129

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 13

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 130

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 131

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 14

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 15

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 16

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 17

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 18

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 19

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 20

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 21

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 22

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 23

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 24

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 25

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 26

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 27

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 28

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 29

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 30

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 31

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 32

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 33

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 34

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 35

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 36

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 38

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 39

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 40

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 41

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 42

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 43

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 44

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 45

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 46

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 47

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 48

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 49

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 50

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 51

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 52

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 53

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 54

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 55

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 56

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 57

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 58

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 59

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 60

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 61

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 62

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 63

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 64

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 65

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 66

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 67

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 68

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 69

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 70

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 71

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 72

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 73

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 74

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 75

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 76

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 77

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 78

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 79

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 80

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 81

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 82

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 83

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 84

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 85

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 86

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 87

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 88

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 89

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 90

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 91

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 92

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 93

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 94

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 95

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 96

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 97

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Bungalow 98

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Bungalow 99

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

NA Plot Without Structure

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space90%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt10%
✅Fire protection and fire safety requirements10%
✅Internal Roads & Footpaths80%
✅Landscaping & Tree Planting10%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)70%
✅Solid Waste Management And Disposal60%
✅Storm Water Drains80%
✅Street Lighting100%
✅Treatment And Disposal Of Sewage And Sullage Water20%
✅Water Supply100%
✅Water conservation /Rain water harvesting100%