Mahalaxmi Nagar Standard

by Mahalaxmi Developers
Certificate SignedP52000007290
Mahalaxmi Nagar StandardProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000007290
Registration No.
REA52000013189
Developer
Mahalaxmi Developers
Project Bank
CANARA BANK
Proposed Possession
2028-12-30
Revised Possession
2028-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
9
Project Area
18123.00 sq.m
Total FSI
54369.00
Approved FSI
43588.83
MahaRERA QR
Mahalaxmi Nagar Standard
MahaRERA — P52000007290
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

BUILDING 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.5812120
100%
1 BHK38.05660
100%
1 BHK43.89660
100%

BUILDING 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.4212120
100%
1 BHK29.85330
100%
1 BHK29.96660
100%
1 BHK38.31330
100%
1 BHK38.38330
100%
1 BHK39.33330
100%
1 BHK40.25330
100%
1 BHK42.47330
100%
1 BHK44.35330
100%
1 BHK46.07321
67%
2 BHK29.98330
100%

BUILDING 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK44.6330
100%
1 RK27.17990
100%
1 RK29.55330
100%
1 RK35.52330
100%

BUILDING 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK44.6660
100%
1 RK27.1718180
100%
1 RK29.55660
100%
1 RK35.52660
100%

BUILDING 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.95330
100%
1 BHK44.6990
100%
1 RK27.1727270
100%
1 RK27.18990
100%
1 RK29.55990
100%
1 RK35.52990
100%

BUILDING 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.28303
0%
1 BHK38.73330
100%
1 RK24.14321
67%
1 RK29.0312
33%
1RK35.06312
33%
2 BHK41.35321
67%
2 BHk41.06312
33%
2 BHk41.87312
33%

BUILDING 8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.5330
100%
1 BHK36.58990
100%
1 RK24.17330
100%
1 RK24.18990
100%

BUILDING 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.47660
100%
1 RK24.1612120
100%
1 RK25.47660
100%

Building 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.58660
100%

Construction Progress

BUILDING 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises97%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 8

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
✅Aminities And Development95%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting80%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)95%
✅Solid Waste Management And Disposal100%
⬜Storm Water Drains
✅Street Lighting100%
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply100%
✅Water conservation /Rain water harvesting100%