List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Mahalxmi City Type D

by Mahalaxmi Builders
Certificate SignedP52000008489
Mahalxmi City Type DProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000008489
Registration No.
REA52000012732
Developer
Mahalaxmi Builders
Project Bank
STATE BANK OF INDIA
Proposed Possession
2028-12-30
Revised Possession
2028-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
7430.00 sq.m
Total FSI
22290.00
Approved FSI
17119.62
MahaRERA QR
Mahalxmi City Type D
MahaRERA — P52000008489
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

Building 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.39660
100%
1 BHK35.6330
100%
1 BHK45.48981
89%
1 BHK45.49330
100%
1 RK27.1921210
100%

Building 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK27.1912120
100%
1 BHK36.58660
100%
1 BHK38.03330
100%
1 BHK39.17660
100%
1 BHK39.76660
100%
1 BHK39.98660
100%
1 BHK40.49660
100%
1 BHK43.87330
100%
1 BHK46.19660
100%
1 BHk45.99660
100%

Building 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK45.48330
100%
1 BHK45.5330
100%
1 BHK45.51330
100%
1 BHK45.52321
67%

Construction Progress

Building 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting100%
✅Open Parking90%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting100%
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply100%
⬜Water conservation /Rain water harvesting