RERA Certificate No.
P99000047637
Developer
Madhukar Kanse
Project Bank
RATNAKAR BANK LTD
Proposed Possession
2027-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1383.06 sq.m
Total FSI
1383.06
MahaRERA QR
Mangalmurti Apartment
MahaRERA — P99000047637
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

MANGALMURTI APARTMENT

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK25.4101
0%
1BHK29.96505
0%
1BHK30.38101
0%
1BHK33.87505
0%
1BHK35.54505
0%
1BHK39.77505
0%
1RK22.64505
0%
1RK22.85505
0%
Shop13.06202
0%
Shop22.1101
0%

Construction Progress

MANGALMURTI APARTMENT

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises10%
Slabs of Super Structure30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
Stilt Floor60%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station20%
⬜Energy managemcnt
✅Fire protection and fire safety requirements20%
✅Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking20%
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal10%
✅Storm Water Drains10%
✅Street Lighting10%
✅Treatment And Disposal Of Sewage And Sullage Water10%
✅Water Supply
✅Water conservation /Rain water harvesting15%