Project Information

RERA Certificate No.
P99000016587
Developer
Matruchhaya Developers
Project Bank
GREATER BANK
Proposed Possession
2023-05-30
Revised Possession
1900-01-01
Extended Possession
2026-12-31
Buildings
7
Project Area
6510.80 sq.m
Total FSI
4883.10
MahaRERA QR
Matruchhaya Heights
MahaRERA — P99000016587
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking2
🅿️Closed Parking4
📅Completion2020-05-31
🚗Open Parking4
🅿️Closed Parking2
📅Completion2020-05-31
🚗Open Parking2
🅿️Closed Parking4
📅Completion2022-05-31
📅Completion2022-05-31
🚗Open Parking2
🅿️Closed Parking4
📅Completion2022-05-31
🚗Open Parking2
🅿️Closed Parking4
📅Completion2022-05-31
🚗Open Parking2
🅿️Closed Parking4
📅Completion2022-05-31

Apartment Configurations

A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL28.03321
67%
RESIDENTIAL28.04615
17%
RESIDENTIAL35.75321
67%
SHOP7.02101
0%
SHOP8.31202
0%
SHOP10.6202
0%
SHOP16.07202
0%

B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL28.03321
67%
RESIDENTIAL28.04651
83%
RESIDENTIAL35.75321
67%
SHOP7.02101
0%
SHOP8.31202
0%
SHOP10.6202
0%
SHOP16.07202
0%

C Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL28.01303
0%
RESIDENTIAL28.0312012
0%
RESIDENTIAL32.06101
0%
RESIDENTIAL32.08101
0%
RESIDENTIAL40.86303
0%
SHOP9.56101
0%
SHOP10.98101
0%
SHOP12.22101
0%
SHOP13.63101
0%
SHOP14.04202
0%
SHOP24.25101
0%

D Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL28.03303
0%
RESIDENTIAL28.04606
0%
RESIDENTIAL32.08101
0%
RESIDENTIAL35.75312
33%
RESIDENTIAL39.8101
0%

E Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL28.01303
0%
RESIDENTIAL28.0312012
0%
RESIDENTIAL32.06101
0%
RESIDENTIAL32.08202
0%
RESIDENTIAL40.86303
0%
RESIDENTIAL46.94101
0%

F Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL28.03303
0%
RESIDENTIAL28.04606
0%
RESIDENTIAL32.08101
0%
RESIDENTIAL35.75303
0%
RESIDENTIAL39.8101
0%

G Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
RESIDENTIAL28.01303
0%
RESIDENTIAL28.0312111
8%
RESIDENTIAL32.06101
0%
RESIDENTIAL32.08101
0%
RESIDENTIAL40.86303
0%
SHOP16.75101
0%
SHOP18.16101
0%
SHOP21.45101
0%
SHOP22.87101
0%
SHOP23.28202
0%
SHOP40.16101
0%

Construction Progress

A Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

B Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

C Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

D Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

E Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

F Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

G Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25%
Stilt Floor75%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure25%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting10%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now