Midtown Bay

by Rising Sun Impex Private Limited Company
Certificate Signed P51900030390
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900030390
Registration No.
REA51900092867
Registration Date
2021-08-17
Developer
Rising Sun Impex Private Limited Company
Project Bank
ICICI BANK LIMITED
Proposed Possession
2027-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
410
Units Sold
353 (86%)
Buildings
1
Project Area
2784.13 sq.m
Total FSI
23376.82
Approved FSI
21423.82
MahaRERA QR
Midtown Bay
MahaRERA — P51900030390
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors51
Sanctioned51
🏠Habitable38
🔢Total Units410
🏡Residential410
⬇️Basements2
🅿️Closed Parking432
📅Completion2027-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 33.90999984741211 0 0 0
0%
1Bhk 34.18000030517578 0 0 0
0%
1Bhk 39.20000076293945 0 0 0
0%
2Bhk 52.029998779296875 0 0 0
0%
2Bhk 52.400001525878906 0 0 0
0%
2Bhk 53.880001068115234 0 0 0
0%

Midtown Bay

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 33.91 112 100 12
89%
1 BHK 34.18 40 16 24
40%
1 BHK 39.2 5 5 0
100%
2 BHK 52.03 104 66 38
63%
2 BHK 52.4 38 10 28
26%
2 BHK 53.88 147 83 64
56%

Construction Progress

Midtown Bay

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises65%
Overall Percentage of Completion of the work done For the entire Building /Wing63%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure95%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Swimming Pool and Fitness Center
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.