Midtown W90

by Midtown Sheltors Llp Partnership
Certificate SignedP51700045256
Midtown W90Project photos will appear here when available.

Project Information

RERA Certificate No.
P51700045256
Registration No.
REA51700101438
Registration Date
2022-05-10
Developer
Midtown Sheltors Llp Partnership
Architect
VITAN CONSULTANTS
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2027-04-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
132
Units Sold
4 (3%)
Buildings
3
Project Area
3900.00 sq.m
Total FSI
14057.89
Approved FSI
4214.51
MahaRERA QR
Midtown W90
MahaRERA — P51700045256
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors31
✅Sanctioned31
🏠Habitable29
🔢Total Units116
🏡Residential116
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units8
🏢Non-Residential8
🏗️Proposed Floors2
✅Sanctioned2
🏠Habitable2
🔢Total Units8
🏡Residential1
🏢Non-Residential7

Apartment Configurations

Building 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK64.56624
33%
2BHK64.65502426
48%
2BHK64.98202
0%
3BHK89.47615
17%
3BHK89.56522626
50%

Building 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Shop29.35835
38%

Building 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Office space29.35808
0%

Construction Progress

Building 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises85%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

Building 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Building 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now