Project Information

RERA Certificate No.
P99000045683
Registration No.
REA99000110577
Registration Date
2022-06-29
Developer
MYZO INFRA PRIVATE LIMITED Company
Architect
Sanjay Maloo
Project Bank
IDFC First Bank Ltd
Proposed Possession
2027-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
7134.02 sq.m
Total FSI
3678.53
Approved FSI
3678.53
MahaRERA QR
MYZO SUITES
MahaRERA — P99000045683
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
Sanctioned5
🚗Open Parking2
📅Completion2027-12-31
🏗️Proposed Floors5
Sanctioned5
🚗Open Parking2
📅Completion2027-12-31
🏗️Proposed Floors5
Sanctioned5
🚗Open Parking2
📅Completion2027-12-31

Apartment Configurations

Building No -1 Type-A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.12 20 0 20
0%

Building No-2 Type-A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.12 20 0 20
0%

Building No-4 Wing A And B Type-B

Type Carpet (sq.ft) Total Booked Available Status
1RK 26.87 7 0 7
0%
1RK 27.32 28 0 28
0%
1RK 29.5 1 0 1
0%
1RK 29.99 4 0 4
0%

Construction Progress

BUILDING NO -1 TYPE-A

Basement (if any)100%

Building No -1 Type-A

Excavation100%

BUILDING NO -1 TYPE-A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No -1 Type-A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO -1 TYPE-A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No -1 Type-A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING NO -1 TYPE-A

Plinth100%
Podiums (if any) 0%

Building No -1 Type-A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO -1 TYPE-A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure25%

Building No -1 Type-A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO -1 TYPE-A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No -1 Type-A

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING NO-2 TYPE-A

Basement (if any)100%

Building No-2 Type-A

Excavation100%

BUILDING NO-2 TYPE-A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No-2 Type-A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO-2 TYPE-A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No-2 Type-A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING NO-2 TYPE-A

Plinth100%
Podiums (if any) 0%

Building No-2 Type-A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO-2 TYPE-A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure45%

Building No-2 Type-A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO-2 TYPE-A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No-2 Type-A

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING NO-4 WING A AND B TYPE-B

Basement (if any)100%

Building No-4 Wing A And B Type-B

Excavation100%

BUILDING NO-4 WING A AND B TYPE-B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No-4 Wing A And B Type-B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO-4 WING A AND B TYPE-B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No-4 Wing A And B Type-B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUILDING NO-4 WING A AND B TYPE-B

Plinth100%
Podiums (if any) 0%

Building No-4 Wing A And B Type-B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO-4 WING A AND B TYPE-B

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No-4 Wing A And B Type-B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO-4 WING A AND B TYPE-B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No-4 Wing A And B Type-B

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space 25%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting 50%
Open Parking 25%
Sewerage (Chamber, Lines, Septic Tank , STP) 25%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting 25%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 25%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.