List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

MYZO SUITES

by MYZO INFRA PRIVATE LIMITED Company
Certificate SignedP99000045683
MYZO SUITESProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000045683
Registration No.
REA99000110577
Registration Date
2022-06-29
Developer
MYZO INFRA PRIVATE LIMITED Company
Architect
Sanjay Maloo
Project Bank
IDFC First Bank Ltd
Proposed Possession
2028-04-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
7134.02 sq.m
Total FSI
3678.53
Approved FSI
3678.53
MahaRERA QR
MYZO SUITES
MahaRERA — P99000045683
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

Building No -1 Type-A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK38.1220020
0%

Building No-2 Type-A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK38.1220020
0%

Building No-4 Wing A And B Type-B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK26.87707
0%
1RK27.3228028
0%
1RK29.5101
0%
1RK29.99404
0%

Construction Progress

BUILDING NO -1 TYPE-A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO-2 TYPE-A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO-4 WING A AND B TYPE-B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space25%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths25%
✅Landscaping & Tree Planting50%
✅Open Parking25%
✅Sewerage (Chamber, Lines, Septic Tank , STP)25%
⬜Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting25%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply25%
⬜Water conservation /Rain water harvesting