Namo Hills - Bldg No 5

by Star Habitat Private Limited
Certificate SignedP51800022947
Namo Hills - Bldg No 5Project photos will appear here when available.

Project Information

RERA Certificate No.
P51800022947
Registration No.
REA51800063250
Developer
Star Habitat Private Limited
Architect
Ellora Project Consultants Pvt Ltd
Project Bank
Kotak Mahindra Bank Ltd
Proposed Possession
2025-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
610.28 sq.m
Total FSI
9845.48
MahaRERA QR
Namo Hills - Bldg No 5
MahaRERA — P51800022947
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
✅Sanctioned25
🏗️Proposed Floors25
✅Sanctioned25
🏗️Proposed Floors25
✅Sanctioned25
🏗️Proposed Floors25
✅Sanctioned25

Apartment Configurations

M1 Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK23.2590090
0%
Shop11.86404
0%

M2 Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK23.2590090
0%
Shop11.86404
0%

M3 Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK23.2590090
0%
Shop11.7101
0%
Shop11.86202
0%
Shop12.03101
0%

M4 Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK23.2590090
0%
Shop11.86202
0%
Shop12.03101
0%
Shop30.56101
0%

Construction Progress

M1 Wing

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

M2 Wing

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

M3 Wing

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

M4 Wing

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Closed Parking
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting