New Haven Boisar II Phase II

by SMART VALUE HOMES (BOISAR) PRIVATE LIMITED Company
Certificate SignedP99000000997
New Haven Boisar II Phase IIProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000000997
Registration No.
REA99000005234
Registration Date
2018-09-04
Developer
SMART VALUE HOMES (BOISAR) PRIVATE LIMITED Company
Architect
Kapadia Associates Design Llp
Project Bank
STATE BANK OF INDIA
Proposed Possession
2020-11-30
Revised Possession
2019-05-31
Extended Possession
2020-11-30
Units Sold
0
Buildings
3
Project Area
14927.42 sq.m
Total FSI
11014.20
Approved FSI
11014.20
MahaRERA QR
New Haven Boisar II Phase II
MahaRERA — P99000000997
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

28

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK58.9710100
100%
2 BHK58.981073
70%
2.5 BHK67.0820164
80%

29

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK58.971082
80%
2 BHK58.981073
70%
2.5 BHK67.0820164
80%

30

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK58.971073
70%
2 BHK58.981073
70%
2.5 BHK67.0820137
65%

Construction Progress

28

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

29

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

30

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Community Buildings28%
✅Electrical meter room, sub-station, receiving station31%
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths16%
✅Landscaping & Tree Planting8%
✅Open Parking
✅Others3%
✅Sewerage (Chamber, Lines, Septic Tank , STP)65%
✅Solid Waste Management And Disposal
✅Storm Water Drains90%
✅Street Lighting10%
✅Treatment And Disposal Of Sewage And Sullage Water80%
✅Water Supply25%
✅Water conservation /Rain water harvesting50%