New Shiv Krupa Chsl Triveni ContourProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800005989
Registration No.
REA51800010267
Developer
Triveni Developers
Project Bank
IDBI BANK
Proposed Possession
2023-12-31
Revised Possession
2019-12-31
Extended Possession
2023-12-31
Units Sold
0
Buildings
1
Project Area
1803.70 sq.m
Total FSI
3837.70
Approved FSI
1412.29
New Shiv Krupa Chsl Triveni Contour
MahaRERA — P51800005989
MahaRERA — P51800005989
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors23
✅Sanctioned23
Apartment Configurations
NEW SHIV KRUPA TRIVENI CONTOUR
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2BHK B WING | 44.67 | 1 | 1 | 0 | 100% |
| 2BHK B WING | 45.67 | 5 | 4 | 1 | 80% |
| 2BHK B WING | 50.79 | 13 | 12 | 1 | 92% |
| 2BHK B WING | 50.8 | 1 | 1 | 0 | 100% |
| 2BHK B WING | 62.6 | 10 | 7 | 3 | 70% |
| 3 BHK A WING | 69.05 | 1 | 1 | 0 | 100% |
| 3 BHK A WING | 81.51 | 1 | 1 | 0 | 100% |
| 3 BHK A WING | 83.46 | 10 | 7 | 3 | 70% |
| 3 BHK B WING | 67.81 | 2 | 2 | 0 | 100% |
| 3 BHK B WING | 68.97 | 1 | 1 | 0 | 100% |
Construction Progress
NEW SHIV KRUPA TRIVENI CONTOUR
RERA Registered Amenities
✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting