Nidhi PalaceProject photos will appear here when available.
Project Information
RERA Certificate No.
P99000004975
Registration No.
REA99000011082
Registration Date
2017-08-09
Developer
Bhagawati Construction Partnership
Architect
Sai Chhaya Associate Shantanu Vichare
Proposed Possession
2018-04-30
Revised Possession
2018-04-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
726.00 sq.m
Total FSI
870.17
Approved FSI
870.17
Nidhi Palace
MahaRERA — P99000004975
MahaRERA — P99000004975
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors5
✅Sanctioned5
Apartment Configurations
Nidhi Palace
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 bhk Flat | 29.88 | 4 | 0 | 4 | 0% |
| 1 bhk Flat | 31.4 | 1 | 1 | 0 | 100% |
| 1 bhk Flat | 32.17 | 4 | 2 | 2 | 50% |
| 1 bhk Flat | 35.35 | 4 | 2 | 2 | 50% |
| 1 bhk Flat | 43.15 | 4 | 1 | 3 | 25% |
| 1 bhk flat | 34.97 | 1 | 0 | 1 | 0% |
| Shop 1 | 32.73 | 1 | 0 | 1 | 0% |
| Shop 2 | 19.4 | 1 | 0 | 1 | 0% |
| Shop 3 | 27.09 | 1 | 1 | 0 | 100% |
Construction Progress
Nidhi Palace
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station50%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)80%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting