Project Information
RERA Certificate No.
P52000055874
Registration No.
REA52000157306
Registration Date
2024-04-29
Developer
MS BUILT HEIGHT LLP Partnership
Architect
A R Yogesh Shelke
Project Bank
ICICI BANK LIMITED
Proposed Possession
2026-12-31
Units Sold
0
Project Area
3360.90 sq.m
Total FSI
3617.13
Approved FSI
3617.13
Niki Tower 2
MahaRERA โ P52000055874
MahaRERA โ P52000055874
Scan to verify on MahaRERA portal
Wing-wise Details
๐๏ธProposed Floors12
โ
Sanctioned12
๐
ฟ๏ธClosed Parking37
๐
Completion2026-12-31
Apartment Configurations
Niki Tower 2
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 30.63 | 14 | 0 | 14 | 0% |
| 1RK | 16.74 | 1 | 0 | 1 | 0% |
| 1RK | 18.37 | 6 | 0 | 6 | 0% |
| 2 BHK | 43.81 | 13 | 0 | 13 | 0% |
| Duplex 3 BHK | 200.71 | 1 | 0 | 1 | 0% |
| Exs Ten 1 BHK | 30.63 | 7 | 0 | 7 | 0% |
| Exs Ten 1 RK | 18.37 | 26 | 0 | 26 | 0% |
| Exs Ten 1 RK | 18.81 | 1 | 0 | 1 | 0% |
| Exs Ten 2 BHK | 43.81 | 5 | 0 | 5 | 0% |
Construction Progress
Niki Tower 2
RERA Registered Amenities
โฌAggregate area of recreational Open Space
โฌCommunity Buildings
โ
Electrical Meter Room, Sub-Station, Receiving Station
โฌEnergy management
โ
Fire Protection And Fire Safety
Requirements
โฌLandscaping & Tree Planting
โฌOpen Parking
โ
Sewerage (Chamber, Lines, Septic Tank , STP)
โฌSolid Waste Management And Disposal
โ
Storm Water Drains
โฌStreet Lighting
โ
Treatment And Disposal Of Sewage And Sullage Water
โ
Water Conservation, Rain water Harvesting
โ
Water Supply