List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Nilgiri Residency

by Sai Vaishnavi Enterprises Partnership
Certificate SignedP51700025000
Nilgiri ResidencyProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700025000
Registration No.
REA51700070324
Registration Date
2021-09-08
Developer
Sai Vaishnavi Enterprises Partnership
Architect
Vijay Pandey (Vijay Pandey & Associates)
Project Bank
BANK OF BARODA
Proposed Possession
2023-06-30
Revised Possession
1900-01-01
Extended Possession
2023-09-30
Units Sold
0
Buildings
2
Project Area
3219.26 sq.m
Total FSI
3219.26
Approved FSI
3219.26
MahaRERA QR
Nilgiri Residency
MahaRERA — P51700025000
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors8
✅Sanctioned8

Apartment Configurations

A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK206.29743
57%
1BHK207.69716
14%
1BHK208.67716
14%
1BHK210.0734
43%
1BHK211.47743
57%
1BHK409.7814410
29%
2BHK278.74734
43%
Shop184.2218513
28%

B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK204.75743
57%
1BHK411.61459
36%
1RK156.24725
29%
Shop62.41606
0%

Construction Progress

A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply100%
✅Water conservation /Rain water harvesting100%