Nirja HeightsProject photos will appear here when available.
Project Information
RERA Certificate No.
P51700051866
Registration No.
REA51700136280
Registration Date
2023-07-07
Developer
Nirja Builders And Developers
Architect
Kt & Associates
Project Bank
THE KALYAN JANATA SAHAKARI BANK LTD.
Proposed Possession
2025-03-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
500.00 sq.m
Total FSI
1566.09
Approved FSI
1566.09
Nirja Heights
MahaRERA — P51700051866
MahaRERA — P51700051866
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors9
✅Sanctioned9
Apartment Configurations
NIRJA HEIGHTS
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 36.36 | 6 | 3 | 3 | 50% |
| 1BHK | 37.49 | 6 | 3 | 3 | 50% |
| 1BHK | 46.0 | 6 | 2 | 4 | 33% |
| 2BHK | 52.37 | 6 | 2 | 4 | 33% |
| Office space | 13.69 | 1 | 0 | 1 | 0% |
| Office space | 46.26 | 1 | 0 | 1 | 0% |
| Office space | 55.49 | 1 | 0 | 1 | 0% |
| Office space | 55.5 | 1 | 0 | 1 | 0% |
| Shop | 28.42 | 2 | 2 | 0 | 100% |
| Shop | 40.65 | 1 | 1 | 0 | 100% |
| Shop | 40.73 | 1 | 1 | 0 | 100% |
Construction Progress
NIRJA HEIGHTS
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
✅Open Parking50%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting100%