18
Units
2024
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Jun 2024
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Shop85–112 ftΒ²On request
1 BHK373–419 ftΒ²On request
2 BHK473–531 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000028343
Registered
2021-09-08
Litigation
None on record
Escrow Bank
BANK OF BARODA
Architect
Sai Chhaya Associates
Total FSI
1284
04

Buildings Β· 1 Wing(s)

Nitya Darpan7 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Palghar West
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

Manojkumar Ramesh ShahPartner
09

Construction Progress

100% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Water Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by Shree Riddhi Siddhi Construction

Naman XanaWorli Β· Sold OutPoddar VasundharaVile Parle East Β· Under ConstructionAvenue 9Vile Parle West Β· Under ConstructionAshirwad ResidencyGhatkopar East Β· Under ConstructionYashreeThane Β· Ready PossessionShreejee MrugarchanaMulund West Β· Ready Possession
15

MahaRERA projects nearby in Palghar West

KIARA109 unitsKANCHAN TRADE CENTRE94 unitsVeena Samrajya - Sector VIII Commercial68 unitsFIA VATIKA60 unitsRAJYOG HEIGHTS56 unitsSAMRIDDHI SQUARE50 unitsSHREEPATI MAHAERA50 unitsFIA AANGAN40 unitsSTAR SIGNATURE CITY - STAR OPAL35 unitsMADHU NEEM BUILDING NO. ONE TYPE A30 unitsSHREE DAYARAM RESIDENCY 1E28 unitsStar Roshan City Building No-5 Wing G24 units
?

Frequently Asked Questions

When is possession of NITYA DARPAN?

As per MahaRERA, proposed possession is Jun 2024.

Is NITYA DARPAN RERA-registered?

Yes β€” MahaRERA registration P99000028343, registered 2021-09-08. No litigations on record.

Who is the developer?

Shree Riddhi Siddhi Construction β€” 265 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Palghar West β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’