Oasis - Tower 1

by Glomore Constructions
Certificate SignedP51800006404
Oasis - Tower 1Project photos will appear here when available.

Project Information

RERA Certificate No.
P51800006404
Registration No.
REA51800010389
Registration Date
2017-08-14
Developer
Glomore Constructions
Architect
Sp Associates
Project Bank
HDFC BANK
Proposed Possession
2021-12-30
Revised Possession
2019-12-31
Extended Possession
2021-12-30
Units Sold
0
Buildings
1
Project Area
635.95 sq.m
Total FSI
19436.82
Approved FSI
16774.45
MahaRERA QR
Oasis - Tower 1
MahaRERA — P51800006404
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors38
✅Sanctioned38

Apartment Configurations

Oasis - Tower 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK Area 157.0764640
100%
2 BHK Area 268.9936351
97%
2 BHK Area 368.6236351
97%
2.5 BHK Area 185.5536324
89%
3 BHK Area 194.3935269
74%

Construction Progress

Oasis - Tower 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises98%
Slabs of Super Structure90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor100%

RERA Registered Amenities

✅2 level podiums100%
✅Aggregate area of recreational Open Space
✅Aggregate area of recreational Open Space50%
✅Amenities
✅Amenities40%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station35%
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt
✅Energy managemcnt80%
✅External Podium20%
✅External Podium80%
✅Fire protection and fire safety requirements
✅Fire protection and fire safety requirements100%
✅Internal Roads & Footpaths70%
✅Landscaping & Tree Planting
✅Landscaping & Tree Planting90%
✅Open Parking
✅Open Parking90%
✅Right of Way100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Sewerage (Chamber, Lines, Septic Tank , STP)90%
✅Solid Waste Management And Disposal
✅Solid Waste Management And Disposal60%
✅Stilt100%
✅Storm Water Drains
✅Storm Water Drains90%
✅Street Lighting
✅Street Lighting90%
✅Treatment And Disposal Of Sewage And Sullage Water
✅Treatment And Disposal Of Sewage And Sullage Water60%
✅Water Supply
✅Water Supply100%
✅Water conservation /Rain water harvesting
✅Water conservation /Rain water harvesting70%