List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Om Aarti

by C H Patil And Sons Llp Partnership
Certificate SignedP51800025281
Om AartiProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800025281
Registration No.
REA51800071200
Registration Date
2023-10-18
Developer
C H Patil And Sons Llp Partnership
Architect
Kulin Patrawala
Project Bank
GS Mahanagar Co-operative Bank Limited, Mumbai
Proposed Possession
2025-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
925.60 sq.m
Total FSI
2968.00
Approved FSI
2968.00
MahaRERA QR
Om Aarti
MahaRERA — P51800025281
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
✅Sanctioned15

Apartment Configurations

OM AARTI

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK35.85110
100%
1BHK35.86110
100%
1BHK37.84880
100%
2BHK50.61220
100%
2BHK52.79110
100%
2BHK54.51541
80%
2BHK68.0101
0%
3BHK70.29440
100%
Shop18.03110
100%
Shop18.41101
0%

Construction Progress

OM AARTI

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now