Ornate Galaxy Phase I
by Sai Ornate Developers
Partnership
Project Information
RERA Certificate No.
P99000008854
Registration No.
REA99000015427
Registration Date
2017-08-19
Developer
Sai Ornate Developers Partnership
Architect
En Con
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2020-10-30
Units Sold
0
Buildings
2
Project Area
1380.86 sq.m
Total FSI
12473.91
Approved FSI
10473.91
Ornate Galaxy Phase I
MahaRERA — P99000008854
MahaRERA — P99000008854
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors16
✅Sanctioned16
🚗Open
Parking20
🅿️Closed Parking18
📅Completion2018-12-31
🏗️Proposed Floors16
✅Sanctioned16
🚗Open
Parking20
🅿️Closed Parking34
📅Completion2018-12-31
Apartment Configurations
Ornate Galaxy A And B
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 4505.0 | 162 | 160 | 2 | 99% |
| Shop | 462.0 | 32 | 27 | 5 | 84% |
Ornate Galaxy C And D
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 4005.0 | 144 | 141 | 3 | 98% |
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 Bhk | 4005.0 | 0 | 0 | 0 | 0% |
| 1 Bhk | 4505.0 | 0 | 0 | 0 | 0% |
| Shop | 462.0 | 0 | 0 | 0 | 0% |
Construction Progress
Ornate Galaxy A And B
Ornate Galaxy A and B
Ornate Galaxy C And D
Ornate Galaxy C and D
RERA Registered Amenities
✅Aggregate area of recreational Open Space100%
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station100%
✅Energy management80%
✅Fire Protection And Fire Safety
Requirements95%
✅Landscaping & Tree Planting95%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)95%
✅Solid Waste Management And Disposal90%
✅Storm Water Drains100%
✅Street Lighting95%
✅Treatment And Disposal Of Sewage And Sullage Water60%
✅Water Conservation, Rain water Harvesting100%
✅Water Supply30%