Palais RoyaleProject photos will appear here when available.
Project Information
RERA Certificate No.
P51900006786
Registration No.
REA51900010244
Registration Date
2021-09-10
Developer
Honest Shelters Private Ltd Company
Architect
Talati & Panthaky Associated Private Limited
Project Bank
YES BANK
Proposed Possession
2024-12-30
Revised Possession
2022-12-30
Extended Possession
2024-12-30
Units Sold
0
Buildings
1
Project Area
28409.57 sq.m
Total FSI
69733.52
Approved FSI
54715.20
Palais Royale
MahaRERA — P51900006786
MahaRERA — P51900006786
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors84
✅Sanctioned84
Apartment Configurations
Palais Royale
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| Type1 | 441.82 | 116 | 46 | 70 | 40% |
| Type2 | 324.82 | 4 | 0 | 4 | 0% |
| Type3 | 393.33 | 4 | 0 | 4 | 0% |
| Type4 | 606.24 | 32 | 25 | 7 | 78% |
| Type5 | 667.12 | 4 | 4 | 0 | 100% |
| Type6 | 4135.27 | 1 | 1 | 0 | 100% |
| Type7 | 3460.14 | 1 | 1 | 0 | 100% |
Construction Progress
Palais Royale
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Community Buildings75%
✅Electrical meter room, sub-station, receiving station20%
✅Electrical meter room, sub-station, receiving station50%
✅Energy managemcnt10%
✅Energy managemcnt25%
✅Fire protection and fire safety requirements10%
✅Fire protection and fire safety requirements70%
✅Internal Roads & Footpaths2%
✅Internal Roads & Footpaths25%
✅Landscaping & Tree Planting
✅Landscaping & Tree Planting20%
⬜Open Parking
✅Open Parking1%
✅Sewerage (Chamber, Lines, Septic Tank , STP)5%
✅Sewerage (Chamber, Lines, Septic Tank , STP)60%
✅Solid Waste Management And Disposal5%
✅Solid Waste Management And Disposal10%
✅Storm Water Drains
✅Storm Water Drains25%
✅Street Lighting
✅Street Lighting10%
✅Treatment And Disposal Of Sewage And Sullage Water5%
✅Treatment And Disposal Of Sewage And Sullage Water25%
✅Water Supply10%
✅Water Supply60%
✅Water conservation /Rain water harvesting50%