PANDURANGPARKProject photos will appear here when available.
Project Information
RERA Certificate No.
P99000020314
Developer
CHAITANYA BUILDERS & DEVELOPERS
Architect
RAJ ASSOCIATES
Project Bank
HDFC BANK
Proposed Possession
2026-10-30
Revised Possession
2026-06-30
Extended Possession
1900-01-01
Total Units
96
Units Sold
91 (95%)
Buildings
16
Project Area
8770.00 sq.m
Total FSI
10768.60
Approved FSI
1578.60
PANDURANGPARK MahaRERA — P99000020314
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units12
🏡Residential12
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units16
🏡Residential16
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units11
🏡Residential11
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units13
🏡Residential13
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units17
🏡Residential17
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units16
🏡Residential16
🏗️Proposed Floors5
✅Sanctioned5
🏠Habitable5
🔢Total
Units11
🏡Residential11
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
Apartment Configurations
BUILD NO 3 B WING PROPOSED
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
32.63
0
0
0
0%
1BHK
35.98
2
0
2
0%
2 BHK
46.41
0
0
0
0%
BUILDING NO 1 A WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1BHK
35.98
18
0
18
0%
BUILDING NO 1 B WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
32.13
5
0
5
0%
1 BHK
35.98
9
0
9
0%
2 BHK
45.17
5
0
5
0%
2 BHK
53.29
9
0
9
0%
BUILDING NO 1 B WING PROPOSED
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
32.13
0
0
0
0%
1 BHK
35.98
1
0
1
0%
2 BHK
45.17
0
0
0
0%
2 BHK
53.29
1
0
1
0%
BUILDING NO 1 C WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
35.98
18
0
18
0%
BUILDING NO 1 C WING PROPOSED
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
35.98
2
0
2
0%
BUILDING NO 2 A WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
27.52
4
0
4
0%
1BHK
26.29
5
0
5
0%
1BHK
26.38
4
0
4
0%
1BHK
27.05
1
0
1
0%
2BHK
35.83
4
0
4
0%
2BHK
36.08
1
0
1
0%
BUILDING NO 2 A WING PROPOSED
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
32.13
0
0
0
0%
1 BHK
32.63
0
0
0
0%
2 BHK
46.41
0
0
0
0%
BUILDING NO 2 B WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1BHK
26.32
4
0
4
0%
1BHK
27.02
1
0
1
0%
1BHK
27.52
8
0
8
0%
1BHK
27.74
2
0
2
0%
1BHK
34.56
4
0
4
0%
2BHK
34.6
1
0
1
0%
2BHK
36.64
8
0
8
0%
2BHK
39.36
1
0
1
0%
BUILDING NO 2 B WING PROPOSED
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1 BHK
32.63
1
0
1
0%
1 BHK
35.98
4
0
4
0%
2 BHK
46.41
1
0
1
0%
BUILDING NO 3 A WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1BHK
26.78
2
0
2
0%
1BHK
27.06
12
0
12
0%
1BHK
28.31
4
0
4
0%
BUILDING NO 3 A WING PROPOSED
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1BHK
27.06
2
0
2
0%
BUILDING NO 3 B WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1BHK
26.22
1
0
1
0%
2BHK
26.36
4
0
4
0%
2BHK
34.13
1
0
1
0%
2BHK
34.47
4
0
4
0%
2BHK
41.42
1
0
1
0%
2BHK
41.93
8
0
8
0%
2BHK
41.98
8
0
8
0%
BUILDING NO 4 A WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1BHK
26.22
4
0
4
0%
1BHK
27.35
2
0
2
0%
1BHK
27.59
8
0
8
0%
2BHK
34.47
4
0
4
0%
2BHK
38.9
1
0
1
0%
2BHK
39.64
8
0
8
0%
BUILDING NO 4 B WING
Type
Carpet (sq.ft)
Total
Booked
Available
Status
1BHK
24.64
1
0
1
0%
1BHK
26.31
4
0
4
0%
1BHK
27.35
2
0
2
0%
1BHK
27.54
8
0
8
0%
1BHK
28.44
8
0
8
0%
2 BHK
34.65
4
0
4
0%
Construction Progress
BUILD NO 3 B WING PROPOSED
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 1 A WING
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
BUILDING NO 1 A WING PROPOSED
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 1 B WING
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
BUILDING NO 1 B WING PROPOSED
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 1 C WING
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
BUILDING NO 1 C WING PROPOSED
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 2 A WING
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
BUILDING NO 2 A WING PROPOSED
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 2 B WING
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
BUILDING NO 2 B WING PROPOSED
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 3 A WING
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%
BUILDING NO 3 A WING PROPOSED
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 3 B WING
Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%
BUILDING NO 4 A WING
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
BUILDING NO 4 B WING
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
RERA Registered Amenities
✅Aggregate area of recreational Open Space
⬜Community Buildings
⬜Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths70%
✅Landscaping & Tree Planting50%
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)95%
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting50%
✅Treatment And Disposal Of Sewage And Sullage Water50%