Project Information
RERA Certificate No.
P51800017635
Registration No.
REA51800041282
Registration Date
2018-08-29
Developer
Panom Developers Llp Partnership
Architect
Arun Kumar Dube
Project Bank
DBS BANK INDIA LIMITED
Proposed Possession
2019-12-31
Revised Possession
1900-01-01
Extended Possession
2021-12-15
Units Sold
0
Buildings
1
Project Area
439.76 sq.m
Total FSI
1520.53
Approved FSI
782.53
Panom Park Phase 1 Wing D
MahaRERA — P51800017635
MahaRERA — P51800017635
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors12
✅Sanctioned12
Apartment Configurations
PANOM PARK PHASE 1 WING D
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 27.87 | 1 | 1 | 0 | 100% |
| 1BHK | 32.51 | 1 | 1 | 0 | 100% |
| 1BHK | 37.16 | 1 | 1 | 0 | 100% |
| 1BHK | 43.94 | 1 | 1 | 0 | 100% |
| 2BHK | 55.25 | 5 | 5 | 0 | 100% |
| 2BHK | 55.39 | 5 | 5 | 0 | 100% |
Construction Progress
PANOM PARK PHASE 1 WING D
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt100%
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal100%
✅Storm Water Drains100%
✅Street Lighting100%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%