PARADISE AVENUEProject photos will appear here when available.
Project Information
RERA Certificate No.
P99000030007
Registration No.
REA99000088961
Registration Date
2025-06-16
Developer
SAI PARADISE DEVELOPERS Partnership
Architect
ROSHAN PATIL & ASSOCIATES
Project Bank
HDFC BANK
Proposed Possession
2027-04-30
Revised Possession
1900-01-01
Extended Possession
2025-05-31
Total Units
36
Units Sold
16 (44%)
Buildings
2
Project Area
439.23 sq.m
Total FSI
2006.32
Approved FSI
2006.32
PARADISE AVENUE
MahaRERA — P99000030007
MahaRERA — P99000030007
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units18
🏡Residential18
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units18
🏡Residential18
Apartment Configurations
BUILDING NO 3 WING A
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 36.2 | 14 | 2 | 12 | 14% |
| 2BHK | 43.59 | 4 | 4 | 0 | 100% |
| SOCIETY OFFICE | 26.99 | 1 | 0 | 1 | 0% |
BUILDING NO 3 WING B
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 36.2 | 14 | 5 | 9 | 36% |
| 2BHK | 43.59 | 4 | 0 | 4 | 0% |
Construction Progress
BUILDING NO 3 WING A
BUILDING NO 3 WING B
RERA Registered Amenities
✅Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply