PARAMOUNT ENCLAVE PHASE 02Project photos will appear here when available.
Project Information
RERA Certificate No.
P99000029540
Developer
GAJANAN BUILDERS & DEVELOPERS
Architect
VASTU SHILP
Project Bank
ICICI BANK
Proposed Possession
2027-04-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
43
Units Sold
20 (47%)
Buildings
1
Project Area
1288.03 sq.m
Total FSI
1688.03
Approved FSI
400.00
PARAMOUNT ENCLAVE PHASE 02
MahaRERA — P99000029540
MahaRERA — P99000029540
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total
Units43
🏡Residential34
🏢Non-Residential9
Apartment Configurations
BUILDING NO 2 WING B TYPE D1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 25.99 | 8 | 2 | 6 | 25% |
| 1BHK | 26.24 | 5 | 0 | 5 | 0% |
| 1BHK | 26.31 | 9 | 5 | 4 | 56% |
| 1RK | 18.84 | 8 | 7 | 1 | 88% |
| 2BHK | 39.64 | 4 | 1 | 3 | 25% |
| Shop | 7.97 | 1 | 1 | 0 | 100% |
| Shop | 8.34 | 1 | 0 | 1 | 0% |
| Shop | 10.35 | 1 | 0 | 1 | 0% |
| Shop | 10.69 | 1 | 0 | 1 | 0% |
| Shop | 10.88 | 1 | 0 | 1 | 0% |
| Shop | 13.78 | 3 | 3 | 0 | 100% |
| Shop | 16.11 | 1 | 0 | 1 | 0% |
Construction Progress
BUILDING NO 2 WING B TYPE D1
RERA Registered Amenities
✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting