List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Park One, Phase I

by Shree Laxmi Enterprises Partnership
Certificate SignedP51700047479
Park One, Phase IProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700047479
Registration No.
REA51700121275
Registration Date
2024-04-04
Developer
Shree Laxmi Enterprises Partnership
Architect
SPACE DESIGNERS
Project Bank
DCB BANK LIMITED
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
220
Units Sold
149 (68%)
Buildings
7
Project Area
8780.00 sq.m
Total FSI
9061.08
Approved FSI
9061.08
MahaRERA QR
Park One, Phase I
MahaRERA — P51700047479
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors79
✅Sanctioned79
🏠Habitable7
🔢Total Units56
🏡Residential56
🏗️Proposed Floors42
✅Sanctioned42
🏠Habitable7
🔢Total Units28
🏡Residential28
🏗️Proposed Floors42
✅Sanctioned42
🏠Habitable7
🔢Total Units28
🏡Residential28
🏗️Proposed Floors36
✅Sanctioned36
🏠Habitable6
🔢Total Units24
🏡Residential24
🏗️Proposed Floors27
✅Sanctioned27
🏠Habitable7
🔢Total Units28
🏡Residential28
🏗️Proposed Floors28
✅Sanctioned28
🏠Habitable7
🔢Total Units28
🏡Residential28
🏗️Proposed Floors29
✅Sanctioned29
🏠Habitable7
🔢Total Units28
🏡Residential28

Apartment Configurations

JASMINE, F WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.59562135
38%

JASMINE, G WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.5928028
0%

JASMINE, H WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.5928721
25%

JASMINE, I WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK29.5924816
33%

ORCHID E WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK37.5228217
75%

ORCHID, C WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK37.52281612
57%

ORCHID, D WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK37.5228199
68%

Construction Progress

JASMINE, F WING

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.62%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.32%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises74%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor100%

JASMINE, G WING

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.62%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.32%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises68%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor100%

JASMINE, H WING

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.62%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.32%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises68%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor100%

JASMINE, I WING

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.62%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.46%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor100%

ORCHID E WING

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

ORCHID, C WING

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

ORCHID, D WING

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Community Buildings50%
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)50%
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now