88
Units
2026
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2026
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Office For378 ft²On request
Shop For464 ft²On request
2 BHK For Landowner2,065 ft²On request
1 RK For Sale4,624 ft²On request
1 BHK For Landowner5,563 ft²On request
2 BHK For Sale5,770 ft²On request
1 BHK For Sale8,717 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Live availability, floor plans & today's price — on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000055908
Registered
2024-04-29
Litigation
None on record
Escrow Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Architect
Megha Urbanscapes
Total FSI
1175
04

Buildings · 1 Wing(s)

Platinum Tower8 floors · — units
05

Land DNA · Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06

Location

📍 Vasai East
0.000000000000000,0.000000000000000
▸ Explore map & Street View — for verified buyers
07

Promoter & Professionals

SIDDHIKA SACHIN PATILPartner
09

Construction Progress

30% avg
Basement (if any)100%
Excavation100%
Plinth100%
X number of Basement(s) and Plinth100%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationEnergy managementLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

📐 Unit floor plans📄 Official e-brochure💳 Payment plans · 20:80 · subvention · current offers

Shared on WhatsApp by our MahaRERA advisor — including the latest builder offers and payment schemes we don't list publicly.

💬 Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

14

More by V M Developers

Dhan NarianKhar West · Under ConstructionHiranandani SandsAlibaug · Under ConstructionJVM OdysseusThane West · Under ConstructionJVM CynergyThane East · Under ConstructionJVM EquinoxThane West · Under ConstructionJVM EmeraldThane West · Under Construction
15

MahaRERA projects nearby in Vasai East

OLYMPUS TOWERS355 unitsLAKE SUPERIOR157 unitsPUSHPRAJ INDUSTRIAL PARK114 unitsImperial Splendora - C and E Wing96 unitsImperial Indrapuram88 unitsSKY HEIGHTSImperial PalmsVIJAY ANAND BUILDING A WING & B WINGManav ResidencyJANAVI PLAZA, JANAVI TOWERVORA ASSOCIATESQUEENS TOWER
?

Frequently Asked Questions

When is possession of PLATINUM TOWER?

As per MahaRERA, proposed possession is Dec 2026.

Is PLATINUM TOWER RERA-registered?

Yes — MahaRERA registration P99000055908, registered 2024-04-29. No litigations on record.

Who is the developer?

V M Developers — 3478 projects tracked on Mumbai Property Exchange. View their track record ▸

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
WhatsAppEnquire ▸
🎯 AI Matchmaker
Tell us what you want in Vasai East — get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
✓ MahaRERA P51900079270★ Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK · ₹56,000/sq.ft · Possession Dec 2031
Learn more ›

📰 Latest Mumbai Property News

View all news →