Project Information
RERA Certificate No.
P51700046917
Registration No.
REA51700118529
Registration Date
2022-09-20
Developer
Shiv Sai Infra
Architect
Mahesh Jagtap And Associates
Project Bank
IDBI BANK
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
683.60 sq.m
Total FSI
2089.95
Approved FSI
2089.95
Pratibha Chs Ltd Proposed Building Named Gps Business Park
MahaRERA — P51700046917
MahaRERA — P51700046917
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors8
✅Sanctioned8
Apartment Configurations
PRATIBHA CHS LTD PROPOSED BUILDING NAMED GPS BUSIN
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| GARAGE | 4.05 | 2 | 0 | 2 | 0% |
| Shop | 10.01 | 1 | 1 | 0 | 100% |
| Shop | 10.59 | 3 | 0 | 3 | 0% |
| Shop | 10.83 | 1 | 1 | 0 | 100% |
| Shop | 11.13 | 4 | 1 | 3 | 25% |
| Shop | 11.78 | 1 | 1 | 0 | 100% |
| Shop | 13.36 | 4 | 2 | 2 | 50% |
| Shop | 15.23 | 5 | 2 | 3 | 40% |
| Shop | 16.02 | 4 | 0 | 4 | 0% |
| Shop | 16.06 | 1 | 1 | 0 | 100% |
| Shop | 17.14 | 7 | 1 | 6 | 14% |
| Shop | 18.66 | 6 | 3 | 3 | 50% |
| Shop | 18.9 | 1 | 0 | 1 | 0% |
| Shop | 19.36 | 7 | 2 | 5 | 29% |
| Shop | 20.21 | 3 | 0 | 3 | 0% |
| Shop | 22.45 | 2 | 0 | 2 | 0% |
| Shop | 22.68 | 1 | 1 | 0 | 100% |
| Shop | 25.46 | 1 | 1 | 0 | 100% |
| Shop | 26.96 | 1 | 0 | 1 | 0% |
| Shop | 28.97 | 2 | 2 | 0 | 100% |
| Shop | 29.67 | 1 | 1 | 0 | 100% |
| Shop | 29.73 | 1 | 1 | 0 | 100% |
| Shop | 34.11 | 1 | 1 | 0 | 100% |
| Shop | 34.92 | 1 | 1 | 0 | 100% |
| Shop | 36.08 | 1 | 1 | 0 | 100% |
| Shop | 40.6 | 1 | 1 | 0 | 100% |
| Shop | 42.47 | 1 | 1 | 0 | 100% |
| Shop | 111.54 | 1 | 1 | 0 | 100% |
Construction Progress
PRATIBHA CHS LTD PROPOSED BUILDING NAMED GPS BUSIN
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
⬜Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting