List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

PRIDECITY PHASE II

by M/s Sathe Schemes Others
Certificate SignedP52000045931
PRIDECITY PHASE IIProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000045931
Registration No.
REA52000111748
Registration Date
2022-06-15
Developer
M/s Sathe Schemes Others
Architect
Kuldip Ramchandra Hajare
Project Bank
STATE BANK OF INDIA
Proposed Possession
2028-11-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
2313.00 sq.m
Total FSI
7055.00
Approved FSI
7055.00
MahaRERA QR
PRIDECITY PHASE II
MahaRERA — P52000045931
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
✅Sanctioned9

Apartment Configurations

BUILDING C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.5314014
0%
1BHK33.4714014
0%
1BHK34.5914014
0%
1BHK39.2314014
0%
2BHK46.6514014
0%
2BHK53.8414014
0%
2BHK58.6914014
0%
Shop18.6202
0%
Shop22.68101
0%
Shop25.35202
0%
Shop28.05101
0%
Shop28.82202
0%
Shop41.33202
0%

Construction Progress

BUILDING C

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
⬜Water conservation /Rain water harvesting