Prime BuildersProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800008911
Registration No.
REA51800016457
Registration Date
2020-06-14
Developer
Prime Builders And Developers Partnership
Architect
Bhupendra Patrawala
Project Bank
DCB BANK LIMITED
Proposed Possession
2022-05-30
Revised Possession
2020-11-30
Extended Possession
2022-05-30
Units Sold
0
Buildings
1
Project Area
728.00 sq.m
Total FSI
2341.41
Approved FSI
1950.41
Prime Builders
MahaRERA — P51800008911
MahaRERA — P51800008911
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors18
✅Sanctioned18
Apartment Configurations
Amil Brothers CHS
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 34.71 | 9 | 9 | 0 | 100% |
| 1BHK | 35.85 | 13 | 10 | 3 | 77% |
| 1BHK | 36.43 | 12 | 9 | 3 | 75% |
| 1BHK | 36.45 | 12 | 9 | 3 | 75% |
| 1BHK | 36.5 | 1 | 1 | 0 | 100% |
| 2BHK | 51.4 | 1 | 1 | 0 | 100% |
| 2BHK | 53.25 | 3 | 3 | 0 | 100% |
| 3BHK | 66.97 | 2 | 2 | 0 | 100% |
| Shop 1 | 26.5 | 2 | 2 | 0 | 100% |
Construction Progress
Amil Brothers CHS
NA Plot Without Structure
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting