R-4 Mankhurd

by Mhada Public Authority
Certificate SignedP51800000034
R-4 MankhurdProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800000034
Registration No.
REA51800001614
Registration Date
2017-06-16
Developer
Mhada Public Authority
Architect
Nitin Patil
Project Bank
BANK OF MAHARASHTRA
Proposed Possession
2019-07-31
Revised Possession
2018-08-22
Extended Possession
2019-07-31
Units Sold
0
Buildings
2
Project Area
3079.94 sq.m
Total FSI
7776.76
Approved FSI
7776.76
MahaRERA QR
R-4 Mankhurd
MahaRERA — P51800000034
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
✅Sanctioned24
🏗️Proposed Floors1
✅Sanctioned1

Apartment Configurations

1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
EWS27.882650265
0%

2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
REHAB13.94606
0%

Construction Progress

1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises85%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor0%

2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting