RAJ BAUG PHASE - III

by NEHALDHARA REALTORS Partnership
Certificate SignedP52000016233
RAJ BAUG PHASE - IIIProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000016233
Registration No.
REA52000036435
Registration Date
2021-09-10
Developer
NEHALDHARA REALTORS Partnership
Architect
Homework
Project Bank
IDBI BANK
Proposed Possession
2026-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
9
Project Area
8179.30 sq.m
Total FSI
10155.00
Approved FSI
10155.00
MahaRERA QR
RAJ BAUG PHASE - III
MahaRERA — P52000016233
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5
🏗️Proposed Floors5
✅Sanctioned5

Apartment Configurations

BUILDING NO 10

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.0101
0%
2 BHK780.017134
76%
SHOP98.0808
0%

BUILDING NO 11

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.0101
0%
2 BHK780.017116
65%
SHOP98.0817
12%

BUILDING NO 12

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.0101
0%
2 BHK780.017116
65%
SHOP98.0808
0%

BUILDING NO 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK1251.0402515
62%

BUILDING NO 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK1251.0403010
75%

BUILDING NO 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK1251.0402614
65%

BUILDING NO 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK595.020911
45%

BUILDING NO 8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK455.015105
67%

BUILDING NO 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.0101
0%
2 BHK780.017413
24%
SHOP98.0808
0%

Construction Progress

BUILDING NO 10

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 11

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 12

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 4

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 5

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 6

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 7

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 8

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 9

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%